Gentlemen: training Department 
The International Training &Consultation Center is pleased to invite you to attend the training program, the information required are in the following:	
FIDIC Claims: Management of Claims and Resolution of Disputes
Objectives 		
•	Understand the claim and dispute resolution procedures under FIDIC Conditions of Contract
•	Recognize practical issues encountered on projects as to claims and disputes, and how to address those
•	Summarize recent FIDIC case law and other authorities as to claims and dispute matters
•	Apply practical/hands-on feedback and insights from an experienced FIDIC practitioner and a claims consultant
•	Demonstrate the necessary knowledge, advice and insights in order to navigate through the FIDIC claim and dispute provisions on their projects
Course outline 		
•	Introduction to FIDIC     
•	General Introduction
•	Introduction to the FIDIC Contracts
•	Managing Variations      
•	Variations covered by Clause 13 and related clauses
•	Definition
•	Initiation and instruction of variations
•	Role of the Engineer
•	FIDIC approach (Construction versus Plant and Design-Build Contract)
•	The Management of Claims
•	Claims: causes and risks
•	Inherent project risks
•	Allocation of risks under FIDIC contracts
•	Analysis of contractual risk
•	Notices and claims procedures
•	Clauses requiring notice by the Contractor
•	Employer’s/Engineer’s claims (Sub-Clause 2.5)
•	Delegation by the Engineer (Sub-Clause 3.2)
•	Contractor’s claims (Sub-Clause 20.1)
•	Notification of claims
•	Contemporary records
•	Preparation of claims
•	Engineer’s assessment and principles of claim
•	Engineers valuation
•	Engineer’s determination (Clause 3.5)
•	Claims for delay
•	Extension of time (Sub-Clause 8.4 and 8.5)
•	Force majeure (Sub-Clause 19.4)
•	Delay damages
•	Claims for additional payment I
•	Ground conditions (Sub-Clause 4.12)
•	Late possession (Sub-Clause 2.1)
•	Breaches of contract
•	Employer’s financial claims 
•	Procedure
•	Delay damages
•	Defects in works and/or design
•	Defects in work and design
•	Retention and bonds
•	The Responsibilities of the Main Parties
•	General Issues
•	The Employer
•	The Engineer
•	The Contractor
•	Termination by the Employer
•	Suspension and Termination by the Contractor
•	Risk and responsibility
•	Force majeure
•	The Resolution of Disputes
•	Dispute Adjudication Board (DAB) principles
•	Types of DAB
•	Guarantees and general obligations of the DAB
•	Nomination of DAB
•	Qualifications and selection of members
•	Cost and Payments to the DAB
•	Dispute Adjudication Board working
•	Appointment Failure to agree Referral to the DAB
•	Presentation of evidence to the DAB
•	The DAB’s decision
•	Post-DAB decision processes
•	Implementation
•	Post-DAB mediation
•	Enforcement
•	Amicable settlement
•	Arbitration
•	Arbitrating Claims
•	ICC Rules
•	Selecting arbitrators
•	Use of experts
FIDIC Claims: Management of Claims and Resolution of Disputes
•	
Registration & Contact information
•	Please sent confirmation letter for attending, to the following contacts:
	
amal@itcegy.com 
	Amal abdulrhman
	Training Advisor 
	00201110056192
If you would like any further information, please don't hesitate to contact me
Training Advisor| amal abdulrhman 
Mob| 00201110056192 
E-Mail| 
amal@itcegy.com
With respect